Home
Framework
Level 1 Tasks
Resources
Getting Started
Working With MAB
Customize
Mission Assurance Baseline v2.10
Mission Area Planning
System Planning
Pre-Award Program Planning
Technical Baseline Development
Program Requirements Planning
Program Software Planning
Acquisition Planning
Acquisition Strategy Development
RFP Development
Program Planning & Systems Engineering
Program Management
Program Assurance
Technical Contract Support
Program Risk Management
Program Configuration Management/Data Management
Program Quality Management
Program Software Management
Program Systems Engineering
Requirements Development
Design Assurance
Manufacture & Build Assurance
Interfaces
Integration & Verification Planning
Integration & Verification Execution
System Transition
System Validation
Operational Transition
Reviews & Audits
Mission Assurance Disciplines
System Safety
Reliability Maintainability Availability
Parts Materials & Processes (PM&P)
Electrical Design Integration
Mechanical Design Integration
Electromagnetic Interference/Electromagnetic Compatibility (EMI/EMC)
Mass Properties
Contamination Control
System Survivability
Supportability (Logistics)
Software Engineering
Cyber Security
Frequency Management
Human Factors Engineering
Environmental, Safety, and Health
Cables and Harnesses
Dead Bus Recovery
Launch Preparation & Integration
Launch Site Integration
Space Segment
Space Segment Systems Engineering
Spacecraft Bus Element
Bus Element Systems Engineering
Structures & Mechanisms Subsystem (SMS)
Structures
Mechanisms & Deployables
Structural Dynamics
Ordnance/Pyrotechnics
Electrical Power & Distribution Subsystem (EPDS)
Thermal Control Subsystem (TCS)
Attitude Control Subsystem (ACS)
Propulsion Subsystem (PS)
Telemetry Tracking & Command Subsystem (TT&C)
Command & Data Handling Subsystem (C&DH)
Fault Management Subsystem (FMS)
Software Subsystem (SS)
Payload Element
Payload Element Systems Engineering
Communications
Optical
Navigation
Hosted Payload
Space Vehicle Ground Support Equipment
Space Operations
Launch System Integration
Space Vehicle Storage
Ground Segment
Ground Segment Program Planning & Management
Ground Segment System Engineering, Integration & Test (SEIT)
Ground Segment Supportability
Ground Segment Software
Ground Segment Hardware
Ground Segment Facilities
Launch Segment (Future Work)
User Segment
User Segment Program Planning & Management
User Segment Systems Engineering
User Segment Integration & Test
Operations
MAB
User Segment
User Segment Program Planning & Management
7.1 - User Segment Program Planning & Management
Tasks
Tasks
Sub-Tasks
Description
References
7.1-1 Assess Spectrum Planning and Allocation
Level 2 Tasks
NA
NA