4.4.4.7-3 Assess Ordnance/Pyrotechnics Requirements Definition |
Level 2 Tasks
|
Ensure that a complete and optimal set of requirements is established based on analysis of mission needs, and that a one to one association exists between source and derived requirements (traceability).
|
Mission Assurance Guide, TOR-2007(8546)-6018, Rev B, Requirements Analysis and Verification Chapter; AIAA S-113-2005, Criteria for Explosive Systems and Devices on Space and Launch Vehicles
|
4.4.4.7-4 Assess Ordnance/Pyrotechnic Design |
Level 2 Tasks
|
Ensure the sufficiency of the conceptual, preliminary, and the detailed design of the system to perform the intended function through all operating conditions and throughout the design life.
|
Mission Assurance Guide, TOR-2007(8546)-6018, Rev B, Design Assurance chapter; AIAA S-113-2005, Criteria for Explosive Systems and Devices on Space and Launch Vehicles
|
4.4.4.7-5 Assess Ordnance/Pyrotechnics Verification Planning |
Level 2 Tasks
|
Ensure plan and process are in place that proves the as-built item complies with the requirements baseline as determined by test, analysis, demonstration, inspection and/or similarity, performed at all levels from the lowest level configuration item to the system.
|
Mission Assurance Guide, TOR-2007(8546)-6018, Rev B, Requirements Analysis and Verification Chapter; AIAA S-113-2005, Criteria for Explosive Systems and Devices on Space and Launch Vehicles
|
4.4.4.7-6 Assess Ordnance/Pyrotechnics Analyses |
Level 2 Tasks
|
Ensure data evaluation is complete and conducted by accepted analytical techniques to determine that the item will meet specified requirements.
|
TOR-2011(8591)-2, Space Vehicle Test and Evaluation Handbook; AIAA S-113-2005, Criteria for Explosive Systems and Devices on Space and Launch Vehicles
|
4.4.4.7-7 Assess Ordnance/Pyrotechnics Manufacturing and Build |
Level 2 Tasks
|
Ensure manufacturing and build processes produce items that meet the specified requirements and design. Ensure the design is accurately translated into a reliable, durable, manufactured/built item using processes that are highly repeatable and error free.
|
Mission Assurance Guide, TOR-2007(8546)-6018, Rev B, Manufacturing Assurance chapter; AIAA S-113-2005, Criteria for Explosive Systems and Devices on Space and Launch Vehicles
|
4.4.4.7-8 Assess Ordnance/Pyrotechnics Interfaces |
Level 2 Tasks
|
Ensure all internal and external interfaces are identified and interactions understood (particularly during design and tradeoff analyses). Ensure applicable interface control documents detail compatibility of interfacing systems or components.
|
TOR-2006(8506)-4494, Space Vehicle Systems Engineering Handbook; AIAA S-113-2005, Criteria for Explosive Systems and Devices on Space and Launch Vehicles
|
4.4.4.7-9 Assess Ordnance/Pyrotechnics Integration and Test Planning |
Level 2 Tasks
|
Ensure process in place whereby components, subassemblies, assemblies, units and subsystems are combined functionally and physically to form and perform as a complete system. Ensure testing verifies requirements and validates unit, subsystem and system performance with sufficient rigor.
|
Mission Assurance Guide, TOR-2007(8546)-6018, Rev B: Integration, Test and Evaluation chapter; TOR-2011(8591)-2, Space Vehicle Test and Evaluation Handbook; AIAA S-113-2005, Criteria for Explosive Systems and Devices on Space and Launch Vehicles
|
4.4.4.7-10 Assess Ordnance/Pyrotechnics Verification Execution and Results |
Level 2 Tasks
|
Ensure analysis, simulation, inspection, and test results provide evidence that the as-built system (including all interfaces) satisfies the requirements and specification baseline.
|
Mission Assurance Guide, TOR-2007(8546)-6018, Rev B: Integration, Test and Evaluation chapter; TOR-2011(8591)-2, Space Vehicle Test and Evaluation Handbook; AIAA S-113-2005, Criteria for Explosive Systems and Devices on Space and Launch Vehicles
|