1.2 - Pre-Award Program Planning

1.2-1 Level 2 Tasks

Tasks Applicable Mission Phases Description SFWC Artifacts References
1.2-1-1 Ensure high level costing estimates are derived from architecture Phase 0 | Ensure government reference system architectures used for cost estimation are consistent with the capability shortfalls allocated to the program. NA Cost / Design Trades and Analyses AFI 63-101 or equivalent
1.2-1-2 Ensure integrated Planning Process Analyses is conducted Phase 0 | Ensure program definition is consistent with Integrated Investment Analyses performed across the mission area. NA NA AFI 63-101 or equivalent
1.2-1-3 Ensure Program Objective Memorandum inputs are submitted Phase 0 | Ensure Program office estimates and POM requests are consistent. NA NA AFI 63-101 or equivalent
1.2-1-4 Ensure AFSPC or applicable program approval Process Reviews are conducted Phase 0 | Ensure POM and budget inputs are timely, well-supported and consistent. NA NA AFI 63-101 or equivalent