1.2.1.1 - Program Requirements Planning

1.2.1.1-5 Level 2 Tasks

Tasks Applicable Mission Phases Description SFWC Artifacts References
1.2.1.1-5-1 Ensure the system concept relative to the allocated spectrum is adequate Phase 0 | Phase A | Ensure the system concept relative to the allocated spectrum to specific service being considered. Ensure there is adequate spectrum available for the designated allocation to support the communication links being considered. NA System CONOPS NA
1.2.1.1-5-2 Ensure appropriate filings (Stage 1, and Stage 2) are submitted Phase 0 | Phase A | Ensure preliminary filing, Stage 1, is submitted during pre-phase A activities, and that Stage 2 submittal is filed at the end of Phase A. NA NA NA