Tasks | Applicable Mission Phases | Description | SFWC | Artifacts | References |
---|---|---|---|---|---|
1.3.1-3-1 Ensure that all risks have been handled | Phase 0 | Phase A | | Handling strategy will determine how resources will be used to manage the program. Many low risks will likely be accepted without any mitigation. | NA | NA | AFI 63-101 and AFPAM 63-128 or equivalent |
1.3.1-3-2 Ensure that all medium to high risks have mitigation strategies | Phase 0 | Phase A | | Mitigation strategies will shape the acquisition strategy, various components of the RFP (SOW, CDRLs), and source selection criteria (Sections L & M). | NA | NA | AFI 63-101 and AFPAM 63-128 or equivalent |