| 2.1.3-5-1 Ensure contractor risk handling plans are reviewed, validated, and implemented |
Phase A |
Phase B |
Phase C |
Phase D1 |
|
Ensure handling plans and actions for program risks are defined. Ensure all risk handling/risk reduction activities are monitored, verified and executed. Ensure mitigation activities are worked at the lowest level appropriate and progress is reported at the risk management board.
|
NA
|
Risk Management Plan
|
Mission Assurance Guide, TOR-2007(8546)-6018, Rev B, Risk Management Chapter: TOR-2005(8583)-4019, Risk Management plan Guide for Space Acquisition Programs.
|
| 2.1.3-5-2 Ensure mitigation plans are incorporated into the baseline |
Phase A |
Phase B |
Phase C |
Phase D1 |
|
Ensure the mitigation plans are incorporated into the baseline with applicable integrated management schedule (IMS) tasks and budget. Ensure all existing tasks are incorporated appropriately.
|
NA
|
Integrated Master Schedule (IMS)
|
Mission Assurance Guide, TOR-2007(8546)-6018, Rev B, Risk Management Chapter: TOR-2005(8583)-4019, Risk Management plan Guide for Space Acquisition Programs.
|
| 2.1.3-5-3 Ensure government program risk handling plans are defined and implemented |
Phase A |
Phase B |
Phase C |
Phase D1 |
|
Ensure handling plans and actions for program risks are defined. Ensure risk handling/risk reduction activities are monitored, verified and executed.
|
NA
|
NA
|
Mission Assurance Guide, TOR-2007(8546)-6018, Rev B, Risk Management Chapter: TOR-2005(8583)-4019, Risk Management plan Guide for Space Acquisition Programs.
|
| 2.1.3-5-4 Ensure completion status of contractor and subcontractor risk handling plans |
Phase B |
Phase C |
Phase D1 |
|
Ensure appropriate documentation in place and made available to customer team
|
NA
|
NA
|
Mission Assurance Guide, TOR-2007(8546)-6018, Rev B, Risk Management Chapter: TOR-2005(8583)-4019, Risk Management plan Guide for Space Acquisition Programs.
|
| 2.1.3-5-5 Ensure completion status of government risk handling plans |
Phase B |
Phase C |
Phase D1 |
|
Ensure appropriate documentation in place that defines completion status.
|
NA
|
NA
|
Mission Assurance Guide, TOR-2007(8546)-6018, Rev B, Risk Management Chapter: TOR-2005(8583)-4019, Risk Management plan Guide for Space Acquisition Programs.
|
| 2.1.3-5-6 Ensure residual contractor risk items are updated and validated against the program baseline |
Phase B |
Phase C |
Phase D1 |
|
Ensure residual (accepted) risk is managed, documented and tracked.
|
NA
|
Integrated Master Plan (IMP)
|
Mission Assurance Guide, TOR-2007(8546)-6018, Rev B, Risk Management Chapter: TOR-2005(8583)-4019, Risk Management plan Guide for Space Acquisition Programs.
|
| 2.1.3-5-7 Ensure residual government risk Items are updated and validated against the program baseline |
Phase B |
Phase C |
Phase D1 |
|
Ensure residual (accepted) risk is managed, documented and tracked.
|
NA
|
Integrated Master Plan (IMP)
|
Mission Assurance Guide, TOR-2007(8546)-6018, Rev B, Risk Management Chapter: TOR-2005(8583)-4019, Risk Management plan Guide for Space Acquisition Programs.
|