2.2.5 - Integration & Verification Planning

2.2.5-5 Level 2 Tasks

Tasks Applicable Mission Phases Description SFWC Artifacts References
2.2.5-5-1 Ensure contractor test capability is adequate Phase A | Phase B | Phase C | Phase D1 | Evaluate the contractor capabilities (e.g. experience with similar programs, resources, expertise, facilities, test equipment, scenarios, automated vs. manual testing etc.) to plan and conduct special and formal multi-segment and system of system testing. Ensure that capability for test is adequate from unit to system level. Ensure Integration Planning is complete for test support, handling, calibration, transportation and vehicle equipment. AFMAN 63-119 A13.2.9 NA Mission Assurance Guide, TOR-2007(8546)-6018, Rev B; AFMAN 63-119 or equivalent