2.2.5 - Integration & Verification Planning

2.2.5-6 Level 2 Tasks

Tasks Applicable Mission Phases Description SFWC Artifacts References
2.2.5-6-1 Ensure ground control test and on-orbit test perceptiveness are evaluated Phase B | Phase C | Phase D1 | Ensure the contractors allocation of ground control tests and on-orbit testing to verify and/or validate functional, performance, and or interface requirements. Ensures that the ground testing is complete and perceptive. Ensure that the ground test program includes space vehicle ground control elements to accomplish space-ground compatibility checks and final ground control acceptance testing. NA Integration and Test Plans; System Test Plan Mission Assurance Guide, TOR-2007(8546)-6018, Rev B