Tasks | Applicable Mission Phases | Description | SFWC | Artifacts | References |
---|---|---|---|---|---|
2.2.5-9-1 Ensure entrance and exit criteria for defined assessment points in the test campaign are defined | Phase B | Phase C | | Key program milestones and major events should be supported by formal periodic assessments with identified reports. | NA | NA | TOR-2009(8583)-8545, Guidelines for Space Systems Critical Gated Events |