2.2.5 - Integration & Verification Planning

2.2.5-9 Level 2 Tasks

Tasks Applicable Mission Phases Description SFWC Artifacts References
2.2.5-9-1 Ensure entrance and exit criteria for defined assessment points in the test campaign are defined Phase B | Phase C | Key program milestones and major events should be supported by formal periodic assessments with identified reports. NA NA TOR-2009(8583)-8545, Guidelines for Space Systems Critical Gated Events
2.2.5-9-2 Ensure I&T schedule as a "Gated" process is evaluated Phase B | Phase C | Phase D1 | Key program milestones and major events should be supported by formal periodic assessments with identified reports. NA NA Mission Assurance Guide, TOR-2007(8546)-6018, Rev B