2.3.16 - Cables and Harnesses

2.3.16-2 Level 2 Tasks

Tasks Applicable Mission Phases Description SFWC Artifacts References
2.3.16-2-1 Ensure contractor identifies cable and harness risks Phase A | Phase B | Phase C | Phase D1 | Ensure all new parts, materials, and processes are identified and flagged as potential risk areas until qualifications are completed. Identify any giver/receiver disconnects as schedule risks. Another potential risk area is EMI/EMC. Test cables and harnesses might be necessary to verify the design. NA NA TOR-2006(8506)-4494, Space Vehicle Systems Engineering Handbook, Electrical Power and Distribution chapter, Cabling section
2.3.16-2-2 Ensure contractor mitigates all cable and harness risks Phase A | Phase B | Phase C | Phase D1 | Ensure all identified risks have a mitigation. Mitigation does not include "monitor" or "wait and see". Mitigation must include a risk burn down plan. NA NA TOR-2006(8506)-4494, Space Vehicle Systems Engineering Handbook, Electrical Power and Distribution chapter, Cabling section