2.3.16-2-1 Ensure contractor identifies cable and harness risks |
Phase A |
Phase B |
Phase C |
Phase D1 |
|
Ensure all new parts, materials, and processes are identified and flagged as potential risk areas until qualifications are completed. Identify any giver/receiver disconnects as schedule risks. Another potential risk area is EMI/EMC. Test cables and harnesses might be necessary to verify the design.
|
NA
|
NA
|
TOR-2006(8506)-4494, Space Vehicle Systems Engineering Handbook, Electrical Power and Distribution chapter, Cabling section
|
2.3.16-2-2 Ensure contractor mitigates all cable and harness risks |
Phase A |
Phase B |
Phase C |
Phase D1 |
|
Ensure all identified risks have a mitigation. Mitigation does not include "monitor" or "wait and see". Mitigation must include a risk burn down plan.
|
NA
|
NA
|
TOR-2006(8506)-4494, Space Vehicle Systems Engineering Handbook, Electrical Power and Distribution chapter, Cabling section
|