2.3.16-5-1 Ensure all cable and harness specifications are included in the Verification Cross Reference Matrix (VCRM) |
Phase B |
Phase C |
|
Ensure the VCRM identifies the method of verification for every requirement. The allowable methods are test, demonstration, inspection, and analysis. Verification by similarity is allow only for design verification/qualification, and not for actual flight hardware verification. Ensure there is a description for each requirement verification stating the scope. (e.g. For the test method, need to state the parameters being measured. For inspection method, need to state the hardware or the documentation being inspected.)
|
NA
|
NA
|
TOR-2006(8506)-4494, Space Vehicle Systems Engineering Handbook, Electrical Power and Distribution chapter, Cabling section
|
2.3.16-5-2 Ensure the Verification Plan includes the Verification Ledger |
Phase B |
Phase C |
|
Ensure the Verification Ledger includes the planned verification completion date, the verification product, and the location of the data supporting the verification product.
|
NA
|
NA
|
TOR-2006(8506)-4494, Space Vehicle Systems Engineering Handbook, Electrical Power and Distribution chapter, Cabling section
|