2.3.1-14-1 Ensure compliance with general design safety requirements and policy Phase C | Phase D1 | Ensure information is covered in the Missile System Pre-launch Safety Package (MSPSP). The MSPSP provides a detailed description of hazardous and safety critical ground support and flight hardware equipment, systems, and materials and their interfaces used in the launch of launch vehicles and payloads; Required media for missile system prelaunch safety approval. Ensure program compliance with Range Safety requirements. SFWC 1.2, SFWC 1.2.1 NA AFSPCMAN 91-710, Range Safety User Requirements Manual
2.3.1-14-2 Ensure launch vehicle flight termination system has an approved redundant design Phase C | Phase D1 | Ensure information is covered in the Missile System Pre-launch Safety Package (MSPSP). SFWC 1.2, SFWC 1.2.1.1 NA AFSPCMAN 91-710, Range Safety User Requirements Manual
2.3.1-14-3 Ensure flight termination system testing is compliant with the testing requirements Phase C | Phase D1 | Ensure information is covered in the Missile System Pre-launch Safety Package (MSPSP). SFWC 1.2, SFWC 1.2.1.2 NA AFSPCMAN 91-710, Range Safety User Requirements Manual
2.3.1-14-4 Ensure flight termination system design reliability meets Range Safety requirements Phase C | Phase D1 | Current reliability of 0.999 or better is the requirement per AFSPC Manual 91-710. SFWC 1.2, SFWC 1.2.1.3 NA AFSPCMAN 91-710, Range Safety User Requirements Manual
2.3.1-14-5 Ensure all Range Safety vehicles employ an airborne range tracking system Phase C | Phase D1 | Current reliability of 0.995 or better is the requirement per AFSPC Manual 91-710. SFWC 1.2, SFWC 1.2.1.4 NA AFSPCMAN 91-710, Range Safety User Requirements Manual
2.3.1-14-6 Ensure compliance with ground operations safety requirements Phase C | Phase D1 | Ensure information is Covered in the Missile System Pre-launch Safety Package (MSPSP). SFWC 1.2, SFWC 1.2.2 NA AFSPCMAN 91-710, Range Safety User Requirements Manual
2.3.1-14-7 Ensure system ground support equipment compliant with industrial safety requirements Phase C | Phase D1 | Assure that Material handling equipment (MHE) used for hazardous operations complies with applicable Range Safety requirements. Ensure Material handling equipment was certified and passed periodic proof loading test prior to use. Ensure Ground support hazardous pressure systems meet Range Safety requirements. A minimum safety factor or an ASME [American Society of Mechanical Engineers], DOT [Department of Transportation] or DOD [Department of Defense] alternative requirement specified with Range Safety concurrence. SFWC 1.2, SFWC 1.2.2.1, SFWC 1.2.2.2, SFWC 1.2.2.3, SFWC 1.2.2.4 NA AFSPCMAN 91-710, Range Safety User Requirements Manual