Tasks Applicable Mission Phases Description SFWC Artifacts References
2.3.2-3-1 Ensure environmental stress screening data applied to the design Phase A | Phase B | Phase C | NA SFWC 2.2.1.2 NA Mission Assurance Guide, TOR-2007(8546)-6018, Rev B, Reliability Chapter
2.3.2-3-2 Ensure Flight and On-orbit lessons learned from prior programs applied to the design Phase A | Phase B | Phase C | Ensure contractor has process for capturing and using lessons learned from earlier programs SFWC 2.2.1.3 NA Why Satellites Fail: Lessons for Mission Success, TOR-2009(8617)-8704
2.3.2-3-3 Ensure Life test data collected and applied to the design Phase A | Phase B | Phase C | Ensure contractor has process for capturing and using lessons learned from earlier programs SFWC 2.2.1.4 NA NA
2.3.2-3-4 Ensure parts selected meet reliability requirements Phase A | Phase B | Phase C | Ensure compliance to the reliability requirements on part quality and or additional screening necessary to support the satisfaction of the reliability prediction requirements. Ensure parts that do not satisfy the derating criteria are identified. NA NA Mission Assurance Guide, TOR-2007(8546)-6018, Rev B, Reliability Chapter; SMC-S-013, Reliability Program for Space Systems, 13 June 2008 (also published as TOR-2007(8583)-6889 under same title) or equivalent; TOR-2006(8583)-5236 rev A, Technical Requirements for Electronic Space Vehicle Parts
2.3.2-3-5 Ensure reliability engineering assists in design assurance activities Phase A | Phase B | Phase C | Ensure reliability engineering assists with the assessment of reliability trade studies, and the assessment of reliability analysis conducted for reliability requirements validation and verification. Ensure the assessment of reliability models, failure modes analysis, and fault tree analysis is considered in the design. Ensure the contractor's reliability organization provides support to the design reviews, configuration audits, and internal design reviews/audits including subsystem and component configuration requirements. NA NA Mission Assurance Guide, TOR-2007(8546)-6018, Rev B, Reliability Chapter; SMC-S-013, Reliability Program for Space Systems, 13 June 2008 (also published as TOR-2007(8583)-6889 under same title) or equivalent