2.3.2 - Reliability Maintainability Availability

2.3.2-4 Level 2 Tasks

Tasks Applicable Mission Phases Description SFWC Artifacts References
2.3.2-4-1 Ensure the critical/limited life items process is assessed for adequacy and completeness Phase A | Phase B | Phase C | Phase D1 | Phase D2 | Ensure the critical items are identified and managed. SFWC 2.1.1.4.3 NA TOR-2009(8591)-13, Space Vehicle Failure Modes, Effects, and Criticality Analysis; Mission Assurance Guide, TOR-2007(8546)-6018, Rev B, Reliability Chapter; SMC-S-013, Reliability Program for Space Systems, 13 June 2008 (also published as TOR-2007(8583)-6889 under same title) or equivalent