2.3.5-4-1 Ensure the as-built critical clearances have been measured and verified |
Phase D1 |
|
Ensure that critical clearances have been identified on the as-built configuration. This should include measuring/verifying the locations of critical clearance locations of the satellite for fairing clearance verification.
|
NA
|
NA
|
TOR-2006(8506)-4494, Space Systems Engineering Handbook, MDI Section
|
2.3.5-4-2 Ensure that agreed upon vent locations and sizes are present in the as-built configuration.
|
Phase D1 |
|
Ensure that agreed upon vent locations and sizes are present in the as-built configuration. Vent locations should be called out in drawings or in contamination control documentation.
|
NA
|
NA
|
TOR-2006(8506)-4494, Space Systems Engineering Handbook, MDI Section
|