2.3.5 - Mechanical Design Integration

2.3.5-4 Level 2 Tasks

Tasks Applicable Mission Phases Description SFWC Artifacts References
2.3.5-4-1 Ensure the as-built critical clearances have been measured and verified Phase D1 | Ensure that critical clearances have been identified on the as-built configuration. This should include measuring/verifying the locations of critical clearance locations of the satellite for fairing clearance verification. NA NA TOR-2006(8506)-4494, Space Systems Engineering Handbook, MDI Section
2.3.5-4-2 Ensure that agreed upon vent locations and sizes are present in the as-built configuration. Phase D1 | Ensure that agreed upon vent locations and sizes are present in the as-built configuration. Vent locations should be called out in drawings or in contamination control documentation. NA NA TOR-2006(8506)-4494, Space Systems Engineering Handbook, MDI Section