2.3.7 - Mass Properties

2.3.7-5 Level 2 Tasks

Tasks Applicable Mission Phases Description SFWC Artifacts References
2.3.7-5-1 Ensure the contractor documents test data records and test results for each critical mass properties test in a test completion report Phase A | Phase B | Phase C | Phase D1 | Ensure the verification and validation that the Final Mass Properties Test Report complies with the program Mass Properties Control Plan, and the test results indicate that all critical mass properties requirements have been met. NA NA ANSI/AIAA S-120A-2015 Mass Properties Control for Space Systems, Section 5.5.5
2.3.7-5-2 Ensure the contractor documents and substantiates the effects on vehicle mass properties resulting from proposed changes submitted with each change proposal Phase A | Phase B | Phase C | Phase D1 | Phase D2 | Ensure evaluation of the effect on Mass Properties for any change proposal submitted after the final mass properties test. NA NA ANSI/AIAA S-120A-2015 Mass Properties Control for Space Systems, Section 5.5.6
2.3.7-5-3 Ensure the contractor develops a mass properties status report format, and submits status reports according to a schedule negotiated with the customer or customer representative Phase A | Phase B | Phase C | Phase D1 | Ensure that the format and content of data in the Mass Properties Status Report complies with program Mass Properties Control Plan and mass properties status reports have been submitted according to schedule. NA NA ANSI/AIAA S-120A-2015 Mass Properties Control for Space Systems, Section 5.5.7