2.3.8-1-1 Ensure evaluation of contamination sources & effects analysis |
Phase A |
Phase B |
Phase C |
|
Ensure identification and itemization of all contamination sensitive system, subsystem and payload elements.
|
NA
|
NA
|
Space Vehicle Systems Engineering Handbook, TOR-2006(8506)-4494, 30 November 2005, Subsection 6.4, Contamination and Contamination Control
|
2.3.8-1-2 Ensure Contamination Control Plan is developed and implemented |
Phase A |
Phase B |
Phase C |
|
Ensure the plan documents means of achieving and verifying cleanliness requirements derived in analysis. Ensure plans are generated for system, subsystem, and/or payload elements and are consistent with interface control document requirements. Contains as a minimum (per ASTM 1548-09): cleanliness requirements for deliverable hardware; implementation plans to achieve, verify and maintain specified cleanliness requirements; environmental controls for facilities to be used; and personnel and operational controls including operating procedures, restrictions, training, and organizational responsibilities for implementation and verification of the Plan.
|
NA
|
NA
|
ASTM E1548-09, Standard Practice for Development of Aerospace Contamination Control Plans
|