4.4.4.5 - Mechanisms & Deployables

4.4.4.5-5 Level 2 Tasks

Tasks Applicable Mission Phases Description SFWC Artifacts References
4.4.4.5-5-1 Ensure test fixture designs are evaluated Phase B | Phase C | Phase D1 | Ensure gravity offloading techniques, vertical deflection limitation on an air-bearing table, etc., do not introduce constraints on deployment. NA NA AIAA S-114-2005
4.4.4.5-5-2 Ensure test fixtures are evaluated for use of safety devices Phase B | Phase C | Phase D1 | Ensure tethers and supports, etc., are used as backup features to preclude damage in the event of failure. NA NA AIAA S-114-2005