4.4.4.7 - Ordnance/Pyrotechnics

4.4.4.7-10 Level 2 Tasks

Tasks Applicable Mission Phases Description SFWC Artifacts References
4.4.4.7-10-1 Ensure adequate acceptance testing was conducted on each production lot, including both destructive and nondestructive acceptance tests Phase C | Phase D1 | Ensure test is executed to plan and results verify requirements. NA NA Space Vehicle Systems Engineering Handbook, TOR-2006(8506)-4494; Space Vehicle Test and Evaluation Handbook, TOR-2011(8591)-2; AIAA S-113-2005, Criteria for Explosive Systems and Devices on Space and Launch Vehicles
4.4.4.7-10-2 Ensure adequate tests were conducted to verify service life extension of components Phase D1 | Ensure test is executed to plan and results verify requirements. NA NA Space Vehicle Systems Engineering Handbook, TOR-2006(8506)-4494; Space Vehicle Test and Evaluation Handbook, TOR-2011(8591)-2; AIAA S-113-2005, Criteria for Explosive Systems and Devices on Space and Launch Vehicles
4.4.4.7-10-3 Ensure thermal vacuum or thermal balance test data is reviewed for component temperatures and thermal control effectivity Phase D1 | Ensure test is executed to plan and results verify requirements. NA NA Space Vehicle Systems Engineering Handbook, TOR-2006(8506)-4494; Space Vehicle Test and Evaluation Handbook, TOR-2011(8591)-2; AIAA S-113-2005, Criteria for Explosive Systems and Devices on Space and Launch Vehicles
4.4.4.7-10-4 Ensure investigation into cause, effect, and corrective action for reject rates above 20% for non destructive test and inspection, or cumulative reject rate of greater than 35% Phase C | Phase D1 | NA NA NA Space Vehicle Systems Engineering Handbook, TOR-2006(8506)-4494; Space Vehicle Test and Evaluation Handbook, TOR-2011(8591)-2; AIAA S-113-2005, Criteria for Explosive Systems and Devices on Space and Launch Vehicles
4.4.4.7-10-5 Ensure qualification test report is assessed Phase D1 | Ensure test is executed to plan and results verify requirements. NA NA AIAA S-113-2005, Criteria for Explosive Systems and Devices on Space and Launch Vehicles
4.4.4.7-10-6 Ensure margin test report is assessed Phase D1 | Ensure test is executed to plan and results verify requirements. NA NA AIAA S-113-2005, Criteria for Explosive Systems and Devices on Space and Launch Vehicles
4.4.4.7-10-7 Ensure lot acceptance test report is assessed Phase D1 | Ensure test is executed to plan and results verify requirements. NA NA AIAA S-113-2005, Criteria for Explosive Systems and Devices on Space and Launch Vehicles
4.4.4.7-10-8 Ensure service life extension test reports are assessed Phase D1 | Ensure testing is executed to plan and results verify requirements. NA NA AIAA S-113-2005, Criteria for Explosive Systems and Devices on Space and Launch Vehicles