4.4.9-4 Level 2 Tasks

Tasks Applicable Mission Phases Description SFWC Artifacts References
4.4.9-4-1 Ensure subsystem design including units, assemblies, sub-assemblies and parts meets the mission performance requirements Phase A | Phase B | Phase C | Pre-Phase A, as applicable, ensure the design satisfies the requirements under the conditions specified by the Design Reference Mission. There should be a realistic worst-case scenario to show that the requirements can be met with margin. Phase A onward, the derived CONOPS should be in a particular document (Flight Requirements and Ops documents) or operations working group products. Some mission concepts may not be directly translated to subsystem requirements in terms of the overall mission operability. The subsystem must be validated against how the components will be used for that particular application. NA NA Space Vehicle Systems Engineering Handbook, TOR-2006(8506)-4494; Mission Assurance Guide, TOR-2007(8546)-6018, Rev B
4.4.9-4-2 Ensure trade studies were conducted and the design baseline satisfies mission requirements and the analysis of alternatives has identified the baseline as the best value Phase A | Phase B | Phase C | Ensure that all trade studies are realizable in terms of technology used and conform to system requirement and physical constraints. Check that viable candidates received appropriate consideration. NA NA Space Vehicle Systems Engineering Handbook, TOR-2006(8506)-4494
4.4.9-4-3 Ensure subsystem technology readiness and risk burn-down plan have been assessed Phase A | Phase B | Phase C | Ensure subsystem technologies, including manufacturing, supplier readiness and programmatic readiness, are mature enough to support the development timeline. Check that the risk mitigation plans are sufficient, funded and conclude at the right time. NA NA Space Vehicle Systems Engineering Handbook, TOR-2006(8506)-4494
4.4.9-4-4 Ensure subsystem hardware and software (as applicable) functions are described in the subsystem specification Phase A | Phase B | Phase C | Ensure that descriptive functions for subsystems and units (including software) are detailed enough for new personnel to understand how the unit or subsystem behaves both individually and within the system. NA NA Space Vehicle Systems Engineering Handbook, TOR-2006(8506)-4494
4.4.9-4-5 Ensure subsystem hardware and software (as applicable) is identified as heritage, modified, or new Phase B | Phase C | Ensure heritage qualification adequacy is documented by analysis and test. NA NA Objective Criteria for Heritage Hardware Reuse, TOR-2010(8591)-19; Reuse of Hardware and Software Products, TOR-2009(8546)-8604
4.4.9-4-6 Ensure all defined contract deliverables and relevant contractor data are complete and accurate to support design reviews Phase A | Phase B | Phase C | Ensure all relevant data is readily available and delivered to support design reviews and design forums. NA NA Space Vehicle Systems Engineering Handbook, TOR-2006(8506)-4494
4.4.9-4-7 Ensure subsystem layout has been provided to include antennas, radio frequency (RF) elements, digital elements, etc. Phase B | Phase C | Ensure that all T&C component specifications are adequate for the environment (such as thermal and mechanical) of their locations. NA NA Space Vehicle Test and Evaluation Handbook, TOR-2011(8591)-2
4.4.9-4-8 Ensure EMC issues are identified and have appropriate mitigation plans Phase B | Phase C | Phase D1 | Ensure that MA EMC spec are flowed down and that the EMC control plan is generated for the TT&C subsystem with emphasis on EMC design and verification at the lowest level of build. Provide summary of, and detailed report (for PDR, present what has been completed, or indicate a due date when the item will be completed). NA NA Space Vehicle Test and Evaluation Handbook, TOR-2011(8591)-2
4.4.9-4-9 Ensure that the system has sufficient capability to recover from any transfer orbit or on-orbit anomaly Phase A | Phase B | Phase C | Ensure antenna provides complete FOV (4 Pi steradian) coverage for recovery and system provides low data rate limited power (low battery) recovery capability. NA NA Space Vehicle Systems Engineering Handbook, TOR-2006(8506)-4494
4.4.9-4-10 Ensure that any potentially systemic design issues are considered for a Design Advisory Phase B | Phase C | Phase D1 | Phase D2 | Phase D3 | Any design or architecture issue that has severe, systemic, or widespread consequences is a potential candidate for a Design Advisory. Design Advisories provide the community with timely and interim notification of an important design issue which may ultimately be captured in a specification or standard. NA NA NA