4.5.7 - Hosted Payload

4.5.7-6 Level 2 Tasks

Tasks Applicable Mission Phases Description SFWC Artifacts References
4.5.7-6-1 Ensure sputtering products resulting from electric propulsion use are modeled to verify their impingement and collection rates on sensitive surfaces of the Hosted Payload are acceptable Phase B | Phase C | Phase D1 | Ensure Hosted Payload modeling includes worst-case conditions and mission degradation over life expectancy. NA NA TOR-2014-02199, Guidelines for Hosted Payload Integration
4.5.7-6-2 Ensure that Hosted Payload design does not allow for outgassing or contamination of sensitive surfaces on the Host Vehicle Phase B | Phase C | Phase D1 | Ensure that COTS products, which are not designed for low outgassing rates, are thoroughly investigated and tested to ensure they will not affect sensitive surfaces of the Host Vehicle. Ensure that appropriate bakeout procedures are performed per Host Vehicle requirements. NA NA TOR-2014-02199, Guidelines for Hosted Payload Integration
4.5.7-6-3 Ensure venting paths are checked to prevent venting into contamination sensitive areas of the Host Vehicle Phase B | Phase C | Phase D1 | Ensure Hosted Payload vent paths are not pointed towards sensitive surfaces on Host Vehicle (e.g., radiators). NA NA TOR-2014-02199, Guidelines for Hosted Payload Integration
4.5.7-6-4 Ensure that the Host Vehicle thruster plumes will not affect contamination-sensitive areas of the Hosted Payload Phase B | Phase C | Phase D1 | Ensure Hosted Payload modeling includes worst-case conditions and mission degradation over life expectancy. NA NA TOR-2014-02199, Guidelines for Hosted Payload Integration
4.5.7-6-5 Ensure apertures and openings of the Hosted Payload are protected to the extent possible and Foreign Object Debris (FOD) control procedures are implemented Phase B | Phase C | Phase D1 | Ensure implementation of FOD control procedures for Hosted Payload development. NA NA TOR-2014-02199, Guidelines for Hosted Payload Integration