4.6 - Space Vehicle Ground Support Equipment

4.6-4 Level 2 Tasks

Tasks Applicable Mission Phases Description SFWC Artifacts References
4.6-4-1 Ensure MGSE FMECAs are performed Phase B | Phase C | Ensure that MGSE transportation and handling equipment failure modes do no harm to space vehicle and are discussed at CDR NA NA TOR-2009(8591)-13, Space Vehicle Failure Modes, Effects, and Criticality Analysis (FMECA) Guide
4.6-4-2 Ensure EGSE FMECAs are performed Phase B | Phase C | Ensure that EGSE interface failure modes do no harm to space vehicle and are discussed at CDR NA NA TOR-2009(8591)-13, Space Vehicle Failure Modes, Effects, and Criticality Analysis (FMECA) Guide
4.6-4-3 Ensure GSE software and control system FMECAs are performed Phase B | Phase C | Ensure that software and control system interface failure modes do no harm to space vehicle and discussed at CDR NA NA TOR-2009(8591)-13, Space Vehicle Failure Modes, Effects, and Criticality Analysis (FMECA) Guide
4.6-4-4 Ensure hazards analysis are performed on safety critical mechanical ground support equipment Phase B | Phase C | Ensure that critical mechanical ground support equipment is identified and preliminary hazards analysis is performed by safety engineers NA NA MIL-STD-882C, System Safety Program Requirements
4.6-4-5 Ensure hazards analysis are performed on safety critical electrical ground support equipment Phase B | Phase C | Ensure that critical electrical ground support equipment is identified and preliminary hazards analysis is performed by safety engineers NA NA MIL-STD-882C, System Safety Program Requirements
4.6-4-6 Ensure hazards analysis are performed on safety critical ground support equipment software and control systems Phase B | Phase C | Ensure that critical ground support equipment software and control systems are identified and preliminary hazards analysis is performed by safety engineers NA NA MIL-STD-882C, System Safety Program Requirements
4.6-4-7 Ensure GSE is discussed at design Reviews Phase B | Phase C | Ensure GSE is line item at PDR and CDR NA NA TOR-2007(8583)-6414 Technical Reviews & Audits