4.9-3-1 Ensure pre-storage and in-storage review of parts/materials/processes (PMP) findings which may affect current and future stored space vehicles, busses, payloads and parts |
Phase D1 |
|
Ensure any findings which potentially affect stored SVs/payloads/parts are considered with the customer for repair/replace actions or additional post-storage testing.
|
SFWC 4.13
|
NA
|
Space Vehicle Systems Engineering Handbook, TOR-2006(8506)-4494; Why Satellites Fail: Lessons for Mission Success, TOR-2009(8617)-8704; Prelaunch Storage of Satellites and Launch Vehicles - 2015 Update, TOR-2016-00732
|
4.9-3-2 Ensure ground test equipment is available and functioning |
Phase D1 |
|
Ensure test equipment is in place and functional at all storage facilities. Ensure regular inspection and stand-alone tests of the equipment are scheduled and executed.
|
SFWC 4.13
|
NA
|
Space Vehicle Test and Evaluation Handbook, Vol. 1, Para. 12.6
|
4.9-3-3 Ensure inspections are performed per the storage plan, and recorded |
Phase D1 |
|
Ensure data are reviewed and assessed, and presented at meetings with the customer.
|
SFWC 4.13
|
NA
|
TOR-2016-00732, Prelaunch Storage of Satellites and Launch Vehicles - 2015 Update
|