5.2.2 - Ground Segment Supportability

5.2.2-4 Level 2 Tasks

Tasks Applicable Mission Phases Description SFWC Artifacts References
5.2.2-4-1 Ensure single-point failures and critical spares/components are identified Phase A | Phase B | Phase C | Phase D1 | Phase D2 | Ensure acquisition documentation includes delivery of analysis (Critical Infrastructure Protection (CIPs), Failure Modes and Effects Criticality Analysis (FMECA), and/or Failure Modes Effects Analysis (FMEAs), etc.) to identify single-point failures and critical spares/components. NA NA Mission Assurance Guide, TOR-2007(8546)-6018, Rev B, Reliability Engineering Chapter
5.2.2-4-2 Ensure contractor maintains trending data on Real Property (RP) & Real Property Installed Equipment (RPIE) failures and outages (metrics) Phase D1 | Phase D2 | Phase D3 | Ensure acquisition documentation includes delivery of trending on failure metrics. NA NA Mission Assurance Guide, TOR-2007(8546)-6018, Rev B, Reliability Engineering Chapter
5.2.2-4-3 Ensure records of root cause failure analyses and remediation actions are maintained for Real Property (RP) & Real Property Installed Equipment (RPIE) failures and outages Phase D1 | Phase D2 | Phase D3 | Ensure acquisition documentation includes delivery of failure analysis and remediation actions database for outages and failures. NA NA Mission Assurance Guide, TOR-2007(8546)-6018, Rev B, Reliability Engineering Chapter
5.2.2-4-4 Ensure new applications are assessed for Parts/Materials/Processes (PMP) impacts to reliability and end of life adjustments Phase C | Phase D1 | Phase D2 | Phase D3 | Ensure all changes are assessed for impacts to reliability and end of life prior to approval. NA NA Mission Assurance Guide, TOR-2007(8546)-6018, Rev B, PMP Chapter
5.2.2-4-5 Ensure ground segment, study efforts, and operational anomaly resolution include appropriate Parts/Materials/Processes (PMP) assessments and guidance Phase C | Phase D1 | Phase D2 | Phase D3 | Ensure Parts/Materials/Processes (PMP) is assessed against all program aspects, not just vehicle hardware. NA NA Mission Assurance Guide, TOR-2007(8546)-6018, Rev B, PMP Chapter; PMP Tech Requirements, SMC-S-010 or equivalent