5.6 - Ground Segment Facilities

5.6-4 Level 2 Tasks

Tasks Applicable Mission Phases Description SFWC Artifacts References
5.6-4-1 Ensure design-supporting analyses are complete and demonstrate compliance with facility requirements Phase B | Phase C | Ensure design reviews are held in accordance with the reference NA Integration and Test Plans Air Force Document (AFD) -070919-027 or equivalent; Unified Facilities Criteria (UFC) 1-200-01 (General Building Requirements)
5.6-4-2 Ensure all project close-out documentation is delivered per design contract requirements and specifications (as-builts) Phase D1 | Ensure final payment is not delivered until this milestone is achieved and deliverables accepted and approved. Deliverables could include as-built drawings, approved parts lists, warranties, operating manuals, certifications, etc. NA NA Air Force Document (AFD) -070919-027 or equivalent; Unified Facilities Criteria (UFC) 1-200-01 (General Building Requirements)