8 - Operations

8-11 Level 2 Tasks

Tasks Applicable Mission Phases Description SFWC Artifacts References
8-11-1 Ensure critical hardware maintenance actions are exercised and evaluated Phase D1 | Phase D2 | Phase D3 | Ensure development and exercise of sustainment processes. These processes should be assessed to determine preparedness for launch. Contractor and/or government maintenance activities must be exercised and reviewed. NA NA Mission Assurance Guide, TOR-2007(8546)-6018, Rev B, Operations Readiness and Mission Operations & Sustainment Chapters
8-11-2 Ensure database installation occurs at all required facilities and are tested Phase D1 | Phase D2 | Phase D3 | Ensure processes are documented and adhered to. NA NA Mission Assurance Guide, TOR-2007(8546)-6018, Rev B, Operations Readiness and Mission Operations & Sustainment Chapters
8-11-3 Ensure inter-site support software compatibility is tested Phase D1 | Phase D2 | Phase D3 | Ensure contractors and government personnel at different facilities use support software which has been tested for compatibility. NA NA Mission Assurance Guide, TOR-2007(8546)-6018, Rev B, Operations Readiness and Mission Operations & Sustainment Chapters
8-11-4 Ensure ground site(s) anomaly response preparations Phase D1 | Phase D2 | Phase D3 | Ensure contractor and government team members have good processes, and follow them, with regard to software problems. Ensure back-up facility and back-up infrastructure are tested, to allow for launch, EOT and emergency operations as required. NA NA Mission Assurance Guide, TOR-2007(8546)-6018, Rev B, Operations Readiness and Mission Operations & Sustainment Chapters
8-11-5 Ensure preparations and testing for flight software uploads Phase D1 | Phase D2 | Phase D3 | Ensure operations has the ability to manage flight software issues, including uploads and testing. Ensure procedures are tested. NA NA Mission Assurance Guide, TOR-2007(8546)-6018, Rev B, Operations Readiness and Mission Operations & Sustainment Chapters
8-11-6 Ensure software licensing Phase D1 | Phase D2 | Phase D3 | Ensure facilities have processes to check for upcoming expirations. Site licenses can expire an inopportune times. NA NA Mission Assurance Guide, TOR-2007(8546)-6018, Rev B, Operations Readiness and Mission Operations & Sustainment Chapters
8-11-7 Ensure integration technical review and content Phase D1 | Phase D2 | Phase D3 | Ensure all facilities involved in operations have reasonable processes for integration and test review, and that they are followed. Ensure that the contractor(s) captures and records technical review decisions. NA NA Mission Assurance Guide, TOR-2007(8546)-6018, Rev B, Operations Readiness and Mission Operations & Sustainment Chapters
8-11-8 Ensure sparing and repair equipment in place Phase D1 | Phase D2 | Phase D3 | Ensure repair equipment is tested. Ensure sparing meets critical availability requirements for both operational test and operations, and that risks and limitations are identified. AFMAN 63-119 A26.5.1 NA Mission Assurance Guide, TOR-2007(8546)-6018, Rev B, Operations Readiness and Mission Operations & Sustainment Chapters; AFMAN 63-119 or equivalent
8-11-9 Ensure logistics scheduling and staffing in place Phase D1 | Phase D2 | Phase D3 | Ensure logistics staff is exercised during rehearsals, and that scheduling is a part of pre-launch operations. NA NA Mission Assurance Guide, TOR-2007(8546)-6018, Rev B, Operations Readiness and Mission Operations & Sustainment Chapters
8-11-10 Ensure crypto key installation/test Phase D1 | Phase D2 | Ensure actual keying material is loaded and tested with data streams expected on-orbit. NA NA Mission Assurance Guide, TOR-2007(8546)-6018, Rev B, Operations Readiness and Mission Operations & Sustainment Chapters
8-11-11 Ensure database compatibility with SV/PL Phase D1 | Phase D2 | Phase D3 | Ensure operations teams have procedures in place to handle changes in telemetry and commands, which need to be sequenced to allow continued operations. NA NA Mission Assurance Guide, TOR-2007(8546)-6018, Rev B, Operations Readiness and Mission Operations & Sustainment Chapters
8-11-12 Ensure pending hardware/facility modifications Phase D1 | Phase D2 | Phase D3 | Ensure upgrades to facilities or contents of the facilities, which are executed through other contracts, are reviewed to determine potential impacts. NA NA Mission Assurance Guide, TOR-2007(8546)-6018, Rev B, Operations Readiness and Mission Operations & Sustainment Chapters