8-7-1 Ensure schedule executability is evaluated |
Phase C |
Phase D1 |
Phase D2 |
|
Ensure loading of system tests, integration, segment tests, hardware tests, training, simulator use, and on-going operations are factored, with margin, early in schedule planning.
|
NA
|
NA
|
Mission Assurance Guide, TOR-2007(8546)-6018, Rev B, Operations Readiness and Mission Operations & Sustainment Chapters
|
8-7-2 Ensure schedule links and completeness is evaluated |
Phase D1 |
Phase D2 |
|
Ensure operations and EOT support are integrated.
|
NA
|
NA
|
Mission Assurance Guide, TOR-2007(8546)-6018, Rev B, Operations Readiness and Mission Operations & Sustainment Chapters
|
8-7-3 Ensure launch/early on-orbit test (EOT) timeline objectives are evaluated |
Phase D1 |
Phase D2 |
|
Ensure timelines are reviewed for completeness of objectives.
|
NA
|
NA
|
Mission Assurance Guide, TOR-2007(8546)-6018, Rev B, Operations Readiness and Mission Operations & Sustainment Chapters
|
8-7-4 Ensure early on-orbit test (EOT) schedule re-plan process is evaluated |
Phase D1 |
Phase D2 |
|
Ensure rehearsals contain sufficient exercising of changes to the overall timeline, to include tasks such as ephemeris collections, commanding windows, external site connectivity, current operations impacts, etc.
|
NA
|
NA
|
Mission Assurance Guide, TOR-2007(8546)-6018, Rev B, Operations Readiness and Mission Operations & Sustainment Chapters
|
8-7-5 Ensure early on-Orbit test (EOT) schedule coordination is completed |
Phase D1 |
Phase D2 |
|
Ensure external agencies are involved with schedule creation and coordination.
|
NA
|
NA
|
Mission Assurance Guide, TOR-2007(8546)-6018, Rev B, Operations Readiness and Mission Operations & Sustainment Chapters
|